I gave an AI agent 12 design review comments. Here is the fix list it built, and where it got it wrong

The original comments, Mira’s complete answer, and an error to catch before assigning the work.

Try Mira for free →
Mira affiliate partner.

Updated: November 16, 2026

Tested 16 Nov 2026 on the free tier with sample data. One attempt.

Also on Medium →

I run an engineering design firm. Every project hits the same step: the review authority sends back a list of comments, and someone has to read each one, work out which drawing it touches, which discipline owns it and who gets the task.

It is not hard work. It is slow work, and it usually lands on the lead engineer.

So I tested whether an AI agent can do the sorting. I used Mira, an agent that runs inside Telegram, on the free tier. I pasted 12 comments for a sample 4-storey office building and added one line:

"Turn these review comments into a fix list: comment, drawing or section affected, discipline, who should fix it, priority. Table."

The prompt and the beginning of Mira’s answer in Telegram
The prompt and the beginning of Mira’s answer in Telegram

What came back

A 12-row table, in the same minute. Each comment got a drawing or section, a discipline, an owner and a priority.

Mira’s actual fix list: rows 5 and 6 in landscape
Mira’s actual fix list: rows 5 and 6 in landscape

Three things were better than I expected:

Mira’s notes on the fix list
Mira’s notes on the fix list

Where it got it wrong

My take

As a first-pass sorter it saves the lead engineer the dullest part of the job. As an engineer it is not one: every row still needs a check before tasks go out. I would use it to draft the fix list and never to issue it.

The reason it fits our workflow is simple: the team already lives in Telegram, and the table lands in the chat where the fixes get discussed.

One limit to know about: the free tier has a monthly message cap. You can try this prompt while your account has allowance available.

Try the prompt in Mira →

Mira affiliate partner.

More prompts for engineering teams: https://mirasteps.com/en/prompts/

The complete prompt to try

Review comments for a 4-storey office building, 3,200 m²: 1. HVAC: supply air rate for the 3rd-floor meeting rooms is below the design occupancy requirement. 2. Electrical: load calculation for panel DB-2 does not include the server room cooling units. 3. Fire safety: smoke exhaust shaft on axis 5/C is missing from the 2nd-floor plan. 4. Plumbing: hot water recirculation line is not shown on the riser diagram. 5. Structural: opening for the ventilation duct in the slab at axis 3/B has no reinforcement detail. 6. HVAC: the heating load table does not match the envelope values in the energy section. 7. Electrical: emergency lighting is not shown on the stair core drawings. 8. Fire safety: fire damper schedule lists 14 dampers, drawings show 16. 9. Plumbing: stormwater outlet invert level conflicts with the site drainage drawing. 10. General: sheet numbering in the HVAC set does not match the drawing register. 11. Electrical: cable tray route crosses the smoke exhaust duct on the 1st floor without a coordination detail. 12. HVAC: no noise calculation for the rooftop units next to the neighbouring residential building. Turn these review comments into a fix list: comment, drawing or section affected, discipline, who should fix it, priority. Table.

Mira’s complete answer — original

The answer below is preserved in English, including the model’s mistakes. The website adapts the table layout for a phone.

Fix List — 4-Storey Office, 3,200 m²

#Review CommentDrawing / Section AffectedDisciplineWho Should FixPriority
1Supply air rate for 3rd-floor meeting rooms below design occupancy requirementHVAC layout & schedule, 3rd floor plan (meeting rooms); Air Change Rate calcHVACHVAC Engineer (design team)High
2Panel DB-2 load calc excludes server room cooling unitsElectrical single-line diagram / panel schedule, DB-2ElectricalElectrical Engineer (EIT to recalc, load owner to confirm CU kW)High
3Smoke exhaust shaft on axis 5/C missing from 2nd-floor planArchitectural floor plan L2 + MEP riser sectionFire Safety / ArchitecturalArchitect (coordination) + Fire Engineer (confirm shaft location/size)High
4Hot water recirculation line not shown on riser diagramPlumbing riser diagram, sheet P-seriesPlumbingPlumbing EngineerMedium
5Ventilation duct opening in slab at axis 3/B has no reinforcement detailStructural slab framing plan / sections, axis 3/BStructuralStructural Engineer (detail) + HVAC (duct size/load)High
6Heating load table does not match envelope U-values in energy sectionHVAC heat load calculations vs. Energy Code / envelope sectionHVACHVAC Engineer (with mechanical energy consultant)Medium
7Emergency lighting not shown on stair core drawingsElectrical lighting plans, stair coresElectricalElectrical Engineer (add luminaires + circuit/feed)High
8Fire damper schedule lists 14 dampers, drawings show 16Fire damper schedule vs. HVAC plansFire Safety / HVACFire Protection Engineer (reconcile both)Medium
9Stormwater outlet invert level conflicts with site drainage drawingSite drainage plan vs. plumbing drainage riserPlumbing / CivilCivil Engineer (site grading) + Plumbing (coordinate levels)Medium
10HVAC sheet numbering does not match drawing registerDrawing register / cover sheet indexHVAC (document control)Document Controller / HVAC LeadLow
11Cable tray route crosses smoke exhaust duct on 1st floor, no coordination detailElectrical tray layout L1 vs. HVAC exhaust shaft plan, axis 5/CElectrical + Fire SafetyElectrical Engineer (reroute/clearance) with Fire Engineer (shaft integrity)High
12No noise calculation for rooftop units next to neighbouring residential buildingHVAC rooftop plant layout, section & site planHVACAcoustics Consultant / HVAC Engineer (prepare NC/ dB(A) calc)Medium

Notes on the list

Likely deadlocks — resolve in a single coordination session (items 3, 5, 11): all three sit on the same shaft/axis system. Fix axis 5/C shaft position first, then the slab penetration at 3/B, then re-route the tray against the resolved exhaust path. Issuing them separately will cause rework.

Items to close with a calculation, not a redline: 1 (air change rate per occupant), 2 (load recalc with CU connected load plus starting current), 6 (reconcile table against envelope), 12 (noise at property line vs. residential criterion, e.g. WHO/NR 45 night-time limits).

Two to sanity-check before issuing as comments:

  • Item 3 — before calling the shaft "missing," check whether it appears on the section or riser only. Many shafts are omitted from the floor plan intentionally to keep it uncluttered. If it's genuinely absent, it becomes an issue, not a markup.
  • Item 8 — the 14 vs 16 discrepancy may be a genuine omission (two dampers never scheduled) or simply a schedule that excludes dampers at the shaft wall. Confirm which before assigning it to the fire engineer.

Sequencing: High items should be reissued as redlines before the next issue date; Medium items can ride the next scheduled revision; item 10 is administrative and can be closed by the document controller.

Want me to convert this into a transmittal-style issue log with due dates and a response column, or draft the cover email to the design team?